2016 - 2017
2016 - 2017
In 2016 the first meeting of the idea-givers takes place. The spark is ignited, in 2017 first draft concepts are established and the local community, as well as second home owners share their opinion in a survey.
2018 -2019
Following a first meeting with Norman Foster, the InnHub La Punt AG is founded in 2018.
With a majority of 88%, the municipal assembly approves the building lease agreement of the InnHub La Punt on April 12th, 2019. The principle of “collavurer” is kicked-off with a first “Inscunter” taking place at the Lyceum Alpinum Zuoz.
2018 - 2019
2020 - 2024
2020 -2024
With a large majority, the partial revision of the new zoning plan is approved by the community.
The InnHub PopUp opens its doors in 2020, a pilot and testing lab for the future InnHub. After the building permit submission, our 2022 “Inscunter” united supporters and partners to advance the InnHub concept.
March 2025
Construction began with the access road and tunnel work at the end of March 2025.
2025
2027
Building Construction
2027
2028
2028
Interior fit-out
December 2028
Plannend Opening in December 2028
2028
2026
Civil works